Client: Education
Sector: Office space
Address: 272 George Street, Sydney
Project Size: 750 sq.m
Contract Value: $560K
Construction Period: 8 weeks

Project Summary:

This project included extensive demolition works of structural walls that required steel beams and posts to ensure no deflection in the slab above. Scope of works were inclusive to new ceilings and floor coverings throughout, work stations, loose furniture, feature joinery, a fully functioning breakout area, meeting rooms, quiet rooms.


1300 020 171

CORPORATE INTERIOR PROJECTS

Find Us

CIP FIT OUT SYDNEY
Suite 5, Level 6,
2-12 Foveaux Street
SURRY HILLS, NSW 2010
T: 1300 020 171

CIP FIT OUT NEWCASTLE
Level 1, Suite 107
17 Bolton Street
NEWCASTLE NSW 2300
T: 02 4910 4051

Find Us

CIP FIT OUT ACT
Level 4, 15 More Street
CANBERRA ACT 2601
T: 02 6169 4099

CIP FIT OUT WOLLONGONG
Level 1, 1 Burelli Street
WOLLONGONG NSW 2500
T: 02 4254 1025

    
Call Now